TCRSD Turkey Creek Ph 2 Branson Creek
Thursday, December 31, 2020
Branson Creek Ph 2 - Flat Creek
More rock breaking on bore pit to occur at MH A37.
9:30am- rock breaking is going good today.
4:33pm- end of day.
Wednesday, December 30, 2020
Branson Creek Ph 2 - Flat Creek
Rock breaking on Bore pit at MH A37 begins today with light rain falling.
1:40pm- first round of rock broke.
5:07pm- A view of the end of the day progress.
Newer Posts
Home
Subscribe to:
Posts (Atom)
Branson Creek Ph 2 - Flat Creek
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.
Branson Creek Ph 2 - Flat Creek
Crew to work on encasement area at STA 2+50. 7:25am- digging is started back now to expose area of encasement. 8:50am- 2 joints of 4” now ...
Branson Creek Ph 2 - Flat Creek
6:35am- crane is here and set up for placing of the wet well base today. 7:00am- crew says another foot or so of rock needs to be broke out...
Branson Creek Ph 2 - Flat Creek
11:28am- bore pit at STA 40+00 shows that the ground has been blasted before and Boring Company is not good with drilling through ruble. 11:...