7:06am- crew will work on D line today again. New holes will be cut in D1 manhole and the wet well to receive 10” pipe.
8:12am- 10” pipe has arrived o site.
9:30am- coring is getting done now at MH D1.
10:33am- LS6 is now cored.
11:39am- rock breaking occurring to get trench opened and to depth between D1 and wetwell.
12:49pm- a little fine tuning taking place so gasket fits better.
1:13pm- 1st joint now placed headed to wetwell from MH D1 with 10” pipe.
2:13pm- 3rd joint placed.
3:46pm- crew prepares to lay last joint into wetwell. A 5’ section was placed before this last 11’-3” piece.
4:04pm- wetwell now connected to line. Crew will gravel and backfill to a point and then begin grouting around gasket on the top to seal connection.