6:57am- crew will be working on D line today at LS6.
7:50am- crew dry stacks MH D1 so that it can be cored to 10” today.
8:50am- some rock breaking has occurred on D line just outside of Liftstaion.
10:38am- 10” line cut cut and a section is removed as crew prepares to glue a cap on the end to be abandoned in place.
11:29am- manhole D1 is now set in place. There is a grade issue though and we are trying to work through it along with the difference in pipe diameters.
1:32pm- crew working on adding a 12” spool to one side for enough to connect to between wetwell and vault.
3:03pm- upright valve going in now as crew cuts more bolts for the short ones needed.
4:16pm- valving and such is complete for today. Crew will begin setting up pump and then pumping down wet well for the rest of today.
4:51pm- wet well is now pumped down.