Thursday, February 25, 2021

Branson Creek Ph 2 - Flat Creek


11:00am- casing is now placed and backfilling roadwY is underway. 

11:55am- roadway is now graveled and base rocked here at STA 49+00.  Roadway will now get opened back up. 

Jere a a few pictures of casing, pipe and rubber boots getting placed from earlier in the morning. 







1:53pm- dozer work now starting in Pinnacle for cleanup. 

3:17pm- more dozing occurs as dump truck hauls off spoil piles today here in Pinnacle. 



3:30pm- clearing for line B is happening now. 

4:05pm- I asked that roadways be swept today in Pinnacle and that the road crossing at STA 40+00 be graded down some so the “bump” would be eliminated. Crews have now completed these tasks. 








No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.