6:43am- hole to begin for wet well at LS6 site today.
8:35am- crew is digging to locate 4” line near STA 41+00.
9:35am- 4” line and 1&1/4” lines located.
9:51am- drilling for blasting on B line now occurring.
10:57am- old 6” forcemain now located.
2:05pm- breaking rock at LS6 site because blasting never broke the rock deep enough.
3:38pm- ARV’s are getting installed today on FM6. Structures are not bituminous coated, so Manufacturer is come come out and coat the three structures at some point.
5:02pm- another ARV going in to round out the day. This time on the 4”.