6:57am- crew will load bore today at MH A37.
9:13am- Coring and cutting is now onsite to core Liftstaion. No pipe will be loaded in bore due to not enough spacers being present onsite.
10:35am- cutting of hole in Liftstaion begins.
11:13am- pipe spacers going on 4” for roadway crossing that is scheduled for this Saturday.
12:24pm- spoke with Chris about cleanup in Pinnacle and what is expected.
1:37pm- trenching in of electrical conduits begins at club house across fairway.
2:15pm- another look at trenching.
-spent the afternoon with Tim and Brad looking at different aspects of the job today. Tie ins, Liftstaions, and Iron Bridge small duplex pump station.
5:18pm- crew discussing approach for tomorrow’s roadway crossing for 4” line at Pinnacle.