6:35am- crane is here and set up for placing of the wet well base today.
7:00am- crew says another foot or so of rock needs to be broke out here on B line before they can start laying pipe.
9:10am- base has finally arrived onsite.
11:05am- wetwell has a 12” anti-float ring around it. The hole that was broke out is too small. The crew has to trim the float ring on two sides to allow it to go into the ground. Crane crew was supposed to be here at 11:00am, but now wont be here until 2pm.
11:53am- still breaking rock on B line at existing manhole.
12:11pm-trimming of float ring is done for wetwell.
2:56pm- well, yet another delay with setting wetwell. Crane can not lift it from the trailer due to it being to far away. Now awaiting a truck to move the trailer.
3:45pm- wetwell is in the air!
3:57pm- LS6 wetwell base now placed.
4:15pm- B line rock is now broke out at existing manhole and ground is leveled where blasting has occurred.
4:50pm- ram-nek is placed on base section of wetwell. Crew will begin stacking it out tomorrow as sections arrive.