Monday, March 8, 2021

Branson Creek Ph 2 - Flat Creek


Crews will work on B line today and place gravel for at LS6 today for setting of wet well tomorrow. 
7:40am- Crew will be pumping water from hole at LS6 site. 

9:13am- B line tie in manhole is dug to expose side so that coring can be done. 

B line is blasted of which was done last week. 

10:26am- hole is pumped down and clean rock is going in now. 



11:42am- gravel is getting graded out now. 

1:28pm- coring existing manhole for line B. 
2:40pm- met with Dennis on Interceptor Ph 2 under bridge due to a complaint from Rittenhouse. I’m have roadway center shot to be able to show Rittenhouse exactly where road is getting built. 

3:30pm- spacers are now installed on the 12” pipe for casing from MH A37 to Liftstaion. 

4:00pm- still breaking rock on B line at existing manhole. 

5:07pm- ditch appears to be broke out back to blasted area now. Crew should begin laying 8” gravity tomorrow here on B line. I have asked that an air up ball be placed in cored hole to keep water and debris out of the line. 