Thursday, March 4, 2021

Branson Creek Ph 2 - Flat Creek


7:05am- crew will make tie in on 4” near STA 16+00 today and backfill to cleanup. 

7:34am- more work with digging out at LS6 site after more blasting that was done yesterday. 

8:25am- ditch is dug to connect pipes now. 

9:40am- connection complete. 4” line is now tied in. Gravel backfill will continue along with cleanup. 

10:54am- crew digs along each side on walkway at clubhouse to see if ground is conducive to using a mole.

12:40pm- mole will not be used under walkway due to rocky ground and worried about breaking walkway. 
Now Currently at MH A3 to pull mandrel from A3 -A1 today to get it off punch list for phase 1. 
I have requested dozer work from here back to tree line at entrance to field due to roughness and such before seed and straw goes down of which is still on same punch list. 

2:07pm- theres been an issue with getting the mandrel put together. 

2:21pm- mandrel now in the linear MH A3. 

2:36pm- mandrel now at MH A2. 

3:13pm- mandrel now pulled to MH A1. All Mandreling now complted fir phase 1. 

3:41pm- all 3 ARV structures have now been coated with a bituminous coating. 



4:00om- crew will sweep and do some miscellaneous cleanup to round out the day. LS6 site is now deep enough for wet well. 
















No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.