Wednesday, March 3, 2021

Branson Creek Ph 2 - Flat Creek


6:43am- 4” roadway crossing will occur today at STA 16+00. 

7:40am- digging begins. 

8:27am- rock breaking occurring. 

10:11am- 1st jalf now ready for plates once dug out. 

11:15am- almost across, but more rock to be broke out for proper depth. 

12:35pm- crew not having to excavate under water line. 

2:08pm- casing with carrier pipe now placed in roadway. Backfill is underway. 

3:20pm- half of the roadway now backfilled. 

3:36pm- boots going on to seal casing. 

4:42pm- roadway now opened back up both ways. Some sweeping with rotary broom to take place next. 

5:10pm- sweeping is now underway. 












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.