Crew to work on encasement area at STA 2+50.
7:25am- digging is started back now to expose area of encasement.
8:50am- 2 joints of 4” now laid as crew digs closer towards encasement area.
10:10am- tying up rebar for encasement.
11:45am- ditch is dug and blocks placed as crew ties more rebar.
1:10pm- cages going in around pipe now. Concrete to be onsite at 3pm today.
2:24pm- my re cleanup today on 6” line.
3:05pm- thrust blocks are getting poured on 6” line near road crossings and also on 4” line.
4:15pm- encasement is now completed near STA 2+50.
4:50pm- crew laid 7 joints today with encasement and thrust blocks poured.