Tuesday, February 23, 2021

Branson Creek Ph 2 - Flat Creek


Crew to work on encasement area at STA 2+50. 
7:25am- digging is started back now to expose area of encasement. 

8:50am- 2 joints of 4” now laid as crew digs closer towards encasement area. 

10:10am- tying up rebar for encasement. 

11:45am- ditch is dug and blocks placed as crew ties more rebar. 

1:10pm- cages going in around pipe now. Concrete to be onsite at 3pm today. 

2:24pm- my re cleanup today on 6” line. 

3:05pm- thrust blocks are getting poured on 6” line near road crossings and also on 4” line. 

4:15pm- encasement is now completed near STA 2+50. 

4:50pm- crew laid 7 joints today with encasement and thrust blocks poured. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.