Wednesday, February 24, 2021

Branson Creek Ph 2 - Flat Creek


7:12am- crew is planning on doing roadway crossing today on 4” line at STA 16+00. 

7:56am- change of plans; now crew will cut roadway at 6” crossing at STA 40+00 and begin digging here today. 

8:55am- road crossing is now underway!

10:18am- slow progress. 

11:07am- a fitting is bolted up to head pipe on towards road cut. 

11:56am- more rock breaking occurring. 

1:47pm- half of roadway now has rock broken out. 

3:15pm- rock is almost broke all the way across roadway now. 

4:13pm- rock breaking now has to occur to get under electrical vault. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.