Thursday, January 21, 2021

Branson Creek Ph 2 - Flat Creek


11:28am- bore pit at STA 40+00 shows that the ground has been blasted before and Boring Company is not good with drilling through ruble.

11:30am- concrete begins going down on encasement at STA 22+20 - 20+62. 

12:00pm- crew has laid 11 joints for today so far. 

1:10pm- been going over maps with Boyce crew on rehab work for Branson Creek sewers. 

2:00pm- encasement is finished and crew lays 15 joints today before stopping due to being at intersection of 6” and 4” tie in. No fittings are here to install it yet. 

Clearing is also being done on 4” force main near LS 6 site. 

2:50pm- bore at MH A37 to Liftstaion 3 is now completed with casing installed. 
Grades were shot and its near perfect!

5:11pm- crew has cleaned up area on forcemain 6 and is getting ready to call it a day. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.