6:53am- pipe crew will resume laying FM6 today.
7:25am- rock has shown up again this morning. More breaking to occur.
8:41am- 2nd joint now placed this morning.
10:17am- 7 joints now placed.
11:15am- bore pit at STA 40+00 is getting dug today.
11:56am- blocks going in for pipe support at encasement above well head.
1:14pm- more blocks placed and bottom rebar cage going in.
2:11pm- 12 joints now placed and bottom rebar cages placed.
3:18pm- the full run of pipe is now through encasement area for well head from STA 22+20 thru 20+62 along with bottom rebar cage. Top rebar cages to begin getting set and tied in place.
4:47pm- top part of cages are now placed over pipe. Crew will clean up here and call it a day.
5:00pm- Bore crew has now pushed all but 23’ of casing into bore at LS 1. They are going to bring machine back to set in hole again to push casing rest of the way.