Tuesday, January 19, 2021

Branson Creek Ph 2 - Flat Creek


7:00am- back to laying pipe on FM 6 today and concrete to arrive this morning for encasement. 

8:50am- still no concrete, but 4 joints have been laid as hammer breaks more rock. 

11:35am- slow day, 6 joints laid so far as rock continues to be broke out. Cleanup follows as the day progresses. Still no concrete for encasement. 



11:56am- concrete has arrived!

12:24pm- encasement done. Gravel will be brought up to grade. 


- At WWTF Phase 1 for final on fence going up and Rip Rap getting placed back by RL Persons. 



1:45pm- Explosive Contractors Inc., blasting to take place here shortly at LS6 site for wet well. 

3:02pm- blasting went off without any issues. Pipe crew has laid 9 joints si far with rock breaking along the way. 

4:30pm- Boring machine had to be lifted out of pit late today due to it breaking the front shaft. Crew will have it back tomorrow to finish last 10’ of reaming. 

5:17pm- 17 pipes laid today. Rock went away just after 9th joint today. 













No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.