Monday, January 18, 2021

Branson Creek Ph 2 - Flat Creek


6:50am- crew will be laying 6” forcemain today along with Bore at LS 1 continuing. 

8:18am- 3 joints laid so far today on FM 6. 

10:00am- breaking rock for ARV structure here on FM 6. 

11:51am- structure going in for ARV. 

1:40pm- rebar cage getting built around pipe for encasement over cart tunnel. 
2:56pm- link seals getting installed on ARV vault. 

4:00pm- link seals now installed and tightened. 

4:20pm- reaming back began today from LS 1 to MH A37. 

4:55pn- 13 joints laid today. Concrete foe encasement has been delayed until tomorrow. 












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.