6:50am- crew will be laying 6” forcemain today along with Bore at LS 1 continuing.
8:18am- 3 joints laid so far today on FM 6.
10:00am- breaking rock for ARV structure here on FM 6.
11:51am- structure going in for ARV.
1:40pm- rebar cage getting built around pipe for encasement over cart tunnel.
2:56pm- link seals getting installed on ARV vault.
4:00pm- link seals now installed and tightened.
4:20pm- reaming back began today from LS 1 to MH A37.
4:55pn- 13 joints laid today. Concrete foe encasement has been delayed until tomorrow.