FM6 work and Bore to LS 1 continues today.
7:34am- grading on FM6 along with 2 joints being laid already for today so far.
9:40am- Boring is going good. Pilot hole almost through. Another 5’ or so to go.
10:25am- pilot bit now through to LS 1. Bit is 14” low.
They will pull back and drill another hole.
-Spent time at WWTF where RL crew has now grouted A1 manhole and has fence contractor lined out with what to do. Next Tuesday RL will return to place Rip Rap.
12:35pm- 10 joints for 200’ are now laid here on FM6.
1:35pm- rock break again on FM 6.
3:33pm- still breaking rock as crew ties tebar for encasement on Monday.
4:59pm- 14 joints are now laid for today. 280’.