7:03am- L.S.1 should be dug out enough, but will be shot for grade once bore crew arrives today.
7:32am- 1st joint of pipe for today now laid in place here on FM6. .
9:04am- Boring contractor is onsite now and grades have been shot and figured for bore. Work will be progressing today with getting pit pumped out and machine set.
9:42am- 5 joints now placed and rock breaking begins.
11:00am- still breaking rock.
11:40am- bore pit is nearing ready. Cribbing is in place now.
2:05pm- still breaking rock on FM6. No more pipe has been laid yet.
2:30pm- Boring contractor is now turning bit.
5:00pm- rock has been broke and a total of 11 joints, 220’ of FM 6 was laid today.