Wednesday, January 13, 2021

Branson Creek Ph 1 - Flat Creek


7:03am- L.S.1 should be dug out enough, but will be shot for grade once bore crew arrives today. 

7:32am- 1st joint of pipe for today now laid in place here on FM6. . 

9:04am- Boring contractor is onsite now and grades have been shot and figured for bore. Work will be progressing today with getting pit pumped out and machine set. 

9:42am- 5 joints now placed and rock breaking begins. 

11:00am- still breaking rock. 

11:40am- bore pit is nearing ready. Cribbing is in place now. 

2:05pm- still breaking rock on FM6. No more pipe has been laid yet. 

2:30pm- Boring contractor is now turning bit. 

5:00pm- rock has been broke and a total of 11 joints, 220’ of FM 6 was laid today. 








 


No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.