7:05am- crew to begin laying force main today after truck is unloaded and tools get gathered.
7:35am- L.S. 1 will be excavated around for receiving pit and tie in from bore to MH A37.
8:59am- excavator finally arrives onsite so digging can begin on force main 6 at STA 39+50 roughly.
10:30am- L.S.1 receiving pit is still getting dug out.
10:37am- 4th joint getting ready to go in for 80’ so far as ditch is checked for depth.
11:40am- joint #6 is now placed.
12:51pm- #9 going in for 180’ laid so far.
2:00pm- 12th joint now in for 240’.
2:30pm- backfill is now started.
3:00pm- #16 getting ready to go in.
4:20pm- rock has to be broke now just in this one spot.
5:00pm- 20th joint getting gravel for 400’ of 6” laid today.