Tuesday, January 12, 2021

Branson Creek Ph 2 - Flat Creek


7:05am- crew to begin laying force main today after truck is unloaded and tools get gathered. 

7:35am- L.S. 1 will be excavated around for receiving pit and tie in from bore to MH A37. 

8:59am- excavator finally arrives onsite so digging can begin on force main 6 at STA 39+50 roughly. 
10:30am- L.S.1 receiving pit is still getting dug out. 

10:37am- 4th joint getting ready to go in for 80’ so far as ditch is checked for depth. 



11:40am- joint #6 is now placed. 

12:51pm- #9 going in for 180’ laid so far.  

2:00pm- 12th joint now in for 240’. 

2:30pm- backfill is now started. 

3:00pm- #16 getting ready to go in. 

4:20pm- rock has to be broke now just in this one spot. 

5:00pm- 20th joint getting gravel for 400’ of 6” laid today. 












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.