Boring contractor to begin mobilizing in today.
11:52am- Fence is getting taken down now around current Liftstaion at Bore crossing location to MHA37.
1:50pm- digging begins at Liftstaion 1 to locate power and forcemain.
4:10pm- pipe is getting laid out for force main.
4:42pm- Force main at L.S.1 has been found under edge of fence as more new force main continues to get laid out.
4:58pm- Access 1 is cleaned up now.