6:58am- crew loading parts that arrived yesterday late.
Crews did not work yesterday due to the rain and lack of parts. More work today on forcemains.
7:26am- crew will work on intersecting forcemains where the 4” and 6” tie together.
9:00am- utilities are being located as crew digs this morning.
10:28am- clearance now under utilities as pipe is getting ran now.
1:10pm- pipe and fittings are installed at 4” to 6” tie in. A reducer is used on 4” side of tee off a short piece of 6”. A Thrust block will be formed next as jack hammers break more rock today.
2:40pm- thrust block now poured in place at 6” tee.
5:00pm- rock breaking still occurring. 1 joint of pipe laid with 6” tee placed and thrust block poured.