Crew will be digging and breaking rock again today on FM6.
8:30am- excavator has located a water/sprinkler line.
10:42am- 4 excavators now working on FM6. A lot of rock breaking occurring.
1:23pm- still breaking rock; hose blown on excavator in foreground, and more water/sprinkler line located again by excavator...
2:10pm- I’ve been with Boyce’s crew today on and off as they navigate the repair list. They have ran a camera down the lines in Fieldstone looking at issues and have found more than is listed. I have instructed them to get with Jamey Keys to get things figured out since more issues are now visible than quantified on the list.
3:57pm- been at new Liftstaion 4? Flatcreek is working on stalling valving and such. Spoke to them about backfill again and to make sure safety grates are installed and permanent ladder in valve vault is placed correctly.
4:30pm- rock breaking has been consistent all day long and will round out the day.