Wednesday, March 10, 2021

Branson Creek Ph 2 - Flat Creek


7:09am- water is getting evacuated from LS6 hole. Crew is awaiting arrival of barrel sections.  

8:50am- crew had to unload more 27” pipe for Interceptor Ph 2. 

9:14am- ARV is getting backfilled and lid i stalled today on 6” line. 

11:37am- 1st barrel section finally going on base. 

1:40pm- Two more pieces to go. 

2:25pm- this will be the last section set here today. 
Crew is now moving to line B to begin laying pipe. 

3:25pm- 2 joint now laid on B line from existing manhole. 



5:00pm- crew has laid 6 joints here today this afternoon. 










No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.