Thursday, March 11, 2021

Branson Creek Ph 2 - Flat Creek


10:02am- crew laying pipe on B line and backfilling. 

10:36- rebar cage going in at STA 1+37. 

11:26am- concrete encasement begins. 

12:20pm- encasement now completed. 

1:15pm- 10th joint going for today as excavator digs out for MH B1. 

2:05pm- grading gravel for MH B1 base. 

2:53pm- MH B1 base now set and pipe is graveled up to it. 11joints laid. 

4:00pm- 12th joint; 1st upstream of MH B1 is now laid in place. 

4:51pm- crew will stop at 13 joints being laid today. 













No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.