Monday, March 15, 2021

Branson Creek Ph 2 - Flat Creek


7:05am- crew is back working on B line today. Transit going back up to get alignment of laser set up. 

8:25am- crew has moved to unload 4 truck loads of 27” pipe. 

8:30am- also valve vault is getting unloaded for LS6. 

10:11am- crew is back on B line and have dug and hit rock that will need broke out. No pipe has been laid today yet. 

12:07pm- 3 joints now placed here on be line for today so far. 

2:45pm- another crew is loading bore pipe at MH A37 today. 

4:22pm- 12” is now in LS3. 

4:50pm- 12” line now connected to MH A37. 

5:23pm- 8 joints were laid here on B line today. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.