Wednesday, March 31, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be back to line testing B line today, but first they’ll be grouting outside of wetwell 10” pipe connection. 
7:30am- Crew has removed excess foam from yesterday,  Spray foam was used to seal up initial gap in offset hole overlap from coring job. The 10” new hole overlapped the original 8” hole. Grout will be mixed and applied over and around the connection now. 

7:46am- grouting is now completed. 

9:09am- crew applies ram-nek to D1 MH so that cone can be set and backfilled today. 

9:17am- cone now placed on D1. 

10:15am- crew is back now on B line to resume testing. 

10:53am- MH B1 now passes vacuum test. 

11:17am- line from B1-B2 is under test. 

11:31am-line passes air test. 

11:52am- line from B2 - LS on test. 

11:59am- line passes air test from B2 - LS. 

12:14pm- MH B2 passes vacuum test. 

1:50pm- crew will set up and air test 10” line now at LS6. 

2:04pm- 10” line up s now under test from D1 to LS6. 

2:14pm- 10” line passes air test. 

2:26pm- MH D1 passes vacuum test. 

3:03pm- MH D1 getting grouted. 

4:20pm-one band is now on drop in MH A26. Another will need installed. 

5:00om- crew is calling it a day. 




















No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.