7:08am- crew gathers buckets for grouting manholes today at A37 and on B-line.
7:42am- grouting to begin here at A37 manhole.
8:13am- A37 is now done.
8:45am- crew not a B2 manhole.
9:29am- MH B2 now grouted.
10:31am- MH B1 now grouted.
12:23pm- existing manhole on B line was washed out with buckets of water so that grouting could be done on the influent line; then they decided to lite a fire in the brush pile. Looks like it will now be the priority!
1:33pm- B line into existing manhole is now grouted.
2:07pm- LS6 valve vault upper section getting set today.
2:37pm- section now placed.
5:07pm- crew worked to get some conduit under sidewalk this afternoon at the clubhouse for electrical out to the new pump station that will be installed later on.