Thursday, April 1, 2021

Branson Creek Ph 2 - Flat Creek


7:08am- crew gathers buckets for grouting manholes today at A37 and on B-line. 

7:42am- grouting to begin here at A37 manhole. 

8:13am- A37 is now done. 

8:45am- crew not a B2 manhole. 

9:29am- MH B2 now grouted. 

10:31am- MH B1 now grouted. 

12:23pm- existing manhole on B line was washed out with buckets of water so that grouting could be done on the influent line; then they decided to lite a fire in the brush pile. Looks like it will now be the priority!

1:33pm- B line into existing manhole is now grouted. 

2:07pm- LS6 valve vault upper section getting set today. 

2:37pm- section now placed. 

5:07pm- crew worked to get some conduit under sidewalk this afternoon at the clubhouse for electrical out to the new pump station that will be installed later on. 












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.