Wednesday, December 30, 2020
Branson Creek Ph 2 - Flat Creek
Rock breaking on Bore pit at MH A37 begins today with light rain falling.
1:40pm- first round of rock broke.
5:07pm- A view of the end of the day progress.
No comments:
Post a Comment
Newer Post
Home
Subscribe to:
Post Comments (Atom)
Branson Creek Ph 2 - Flat Creek
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.
Branson Creek Ph 2 - Flat Creek
11:00am- casing is now placed and backfilling roadwY is underway. 11:55am- roadway is now graveled and base rocked here at STA 49+00. Road...
Branson Creek Ph 2 - Flat Creek
No work onsite today.
Branson Creek Ph 2 - Flat Creek
7:06am- crew will work on D line today again. New holes will be cut in D1 manhole and the wet well to receive 10” pipe. 8:12am- 10” pipe ha...