Monday, May 3, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working to get tie-ins done for 6” forcemain and 4” forcemain. 
7:26am- a hole is drilled into the two 4” pipes so that the Liftstaion can be ran to see exactly which pipe is live. The blue line is the live pipe so it will be tied to existing 6” across the service road and by the sidewalk. 

11:26am- old FM6 is exposed today for possible tie in. 

Crew tightening fittings at this time also. 






No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.