Monday, May 24, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on getting 2” line the last couple of hundred feet today. 

11:20am- 2” pipe is now ran and cleanup ensues. 





3:16pm- Boyce has applied an air test on the 3900’ of 6” from FieldStone to top of the hill at pool house. 56 minute test is now underway. 



4:12pm- line passes air test. 







No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.