Branson Creek Ph 2 - Flat Creek


Paving to be done on Phase 1 at Mr. Heads property and LS6 to het more attention today. 
7:40am- Paving crew has arrived on Heads property. 



8:25am- 1st load of asphalt down.



8:53am- almost done with first lift on roadway. 

9:55am- to the top now. 96.97 tons laid so far. 

10:52am- almost finished with second pass. 

11:05am- lat truck! 175.01 tons used today. Property owner is extremely happy!














No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.