Paving to be done on Phase 1 at Mr. Heads property and LS6 to het more attention today.
7:40am- Paving crew has arrived on Heads property.
8:25am- 1st load of asphalt down.
8:53am- almost done with first lift on roadway.
9:55am- to the top now. 96.97 tons laid so far.
10:52am- almost finished with second pass.
11:05am- lat truck! 175.01 tons used today. Property owner is extremely happy!