Branson Creek Ph 2 - Flat Creek
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.
-
Crew to work on encasement area at STA 2+50. 7:25am- digging is started back now to expose area of encasement. 8:50am- 2 joints of 4” now ...
-
6:35am- crane is here and set up for placing of the wet well base today. 7:00am- crew says another foot or so of rock needs to be broke out...
-
11:28am- bore pit at STA 40+00 shows that the ground has been blasted before and Boring Company is not good with drilling through ruble. 11:...