7:50am-No crew working at this time. All personnel working on punch list on Phase 1 Turkey Creek.
4:15pm- more rock is broke out at MH A37 for bore pit.
Also at this time more silt soxx has been placed.
4:30pm- staking for FM 6 was done today.
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.