Monday, February 1, 2021

Branson Creek Ph 2 - Flat Creek


6:58am- crew back to work on FM6 this week. 

7:51am- digging is now underway to start laying pipe this AM. 

10:00am- 6 joints now laid so far as more rock is broke out to a deeper depth. 

11:27am- 9 joints now placed. 

12:29pm- Rehab work by Boyce has begun today with digging up line in Iron Ridge at MH IR1I, #5 item (a) on the list. A short piece of pipe and 2 knock ons are used for the repair. 

Bad piece of pipe internally. 

3:00pm- 17 joints in so far as 18th will be placed with test cap on the end for testing of line at a later date. 

4:36pm- cleanup and backfill occurring now and will round out the day here on FM6. 










No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.