6:58am- crew back to work on FM6 this week.
7:51am- digging is now underway to start laying pipe this AM.
10:00am- 6 joints now laid so far as more rock is broke out to a deeper depth.
11:27am- 9 joints now placed.
12:29pm- Rehab work by Boyce has begun today with digging up line in Iron Ridge at MH IR1I, #5 item (a) on the list. A short piece of pipe and 2 knock ons are used for the repair.
Bad piece of pipe internally.
3:00pm- 17 joints in so far as 18th will be placed with test cap on the end for testing of line at a later date.
4:36pm- cleanup and backfill occurring now and will round out the day here on FM6.