Tuesday, February 2, 2021

Branson Creek Ph 2 - Flat Creek


7:18am- crew has moved equipment over into Pinnacle now so that the 4” line can begin getting laid. 

7:52am- an electric line has been hit and broken near DRA 15+25. 

9:07am- rock will need to be broke out here at the top of ditch. 

10:57am- rock is broke out now and getting dug. More rock will need broke, but this gets them started downhill now. 

11:41am- gravel now going in on 4” pipe being laid. 

1:22pm- Boyce, working on rehab in Pinnacle today have raised MH’s P1E &P1F (map 5) 6” and 12” respectively. 



3:00pm- rock breaking occurring around 8” water line now. 

5:14pm- 8 joints of 4” was laid today on FM4. 















No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.