Wednesday, February 3, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be back digging and laying 4” line today in Pinnacle. 
7:30am- a road crossing will occur today so the crew has closed the road this morning. 

8:36am- road is dug and water line is located, but rock will need to be broken out. 

11:49am- 1st joint laid today on 4” forcemain as crew prepares to begin crossing the road. 

More cleanup getting done on FM6 also at this time. 


-Pre-construction meeting for Phase 2 Turkey Creek took place today2:30-3:30pm

3:45pm- road crossing is done and 45* bends will be thrust blocked yet today. 9 joints laid today with more rock breaking occurring at this time. 

5:25pm- thrust blocks on 4” Forcemain going in now. This will end the day. 







No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.