7:13am- another thrust block will be made today on 4” line as cleanup and rock breaking continues.
8:38am- thrust block now put in place.
10:16am- roadways inside Pinnacle are getting swept today!
11:23am- Boyce crew has now fixed 1 of the broken taps from MH P1B - P1C per sheet 4 b.).
12:56pm- Flatcreek is spot digging for a water line crossing on 4” pipe run.
3:43pm- The old 6” forcemain line that Boyce Excavating is to test is now under test for the next two hours.
3:52pm- Flatcreek crew is still breaking rock. No pipe has been laid today.
5:30pm- another water line is located to distance new sewer line from in Pinnacle.
5:45pm- test on old 6” line by Boyce crew passes two hour test.
No comments:
Post a Comment