Thursday, February 4, 2021

Branson Creek Ph 2 - Flat Creek


7:13am- another thrust block will be made today on 4” line as cleanup and rock breaking continues. 

8:38am- thrust block now put in place. 

10:16am- roadways inside Pinnacle are getting swept today!

11:23am- Boyce crew has now fixed 1 of the broken taps from MH P1B - P1C per sheet 4 b.). 

12:56pm- Flatcreek is spot digging for a water line crossing on 4” pipe run. 

3:43pm- The old 6” forcemain line that Boyce Excavating is to test is now under test for the next two hours. 

3:52pm- Flatcreek crew is still breaking rock. No pipe has been laid today. 

5:30pm- another water line is located to distance new sewer line from in Pinnacle. 

5:45pm- test on old 6” line by Boyce crew passes two hour test. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.