6:58am- crew will be laying pipe on 4” forcemain today. More Rock was broke out last Friday.
7:38am- 1st joint of 4” going in now to start off the day.
9:10am- 5 joints of 4” now placed.
10:11am- 10 joints now laid.
10:40am- 12 joints laid today and laborers are headed home due to approaching weather. Excavator will dig to expose more rock to break.
11:37am- only one guy went home as others will continue to dig and spot utilities.
12:58am- electric has now been located. Excavator will now break rock rest of the day. Another guy is sent home. No more pipe to be laid today.
1:15pm- I will be headed offsite for rest of today.