7:00am- crew will be digging to lay pipe today on 4” line in Pinnacle.
8:11am- 1st joint is preparing to be laid.
9:30am- 5 joints have been placed as more rock will be broke now for crossing in roadway.
11:13am- more rock breaking occurs.
11:40am- Boyce Excavating fixed MH P8A on map 5 by raising it 18” due to it being lower than the creek.
12” barrel section and 6” adjustment ring.
1:25pm- fittings for turn are bolted to pipe now at STA 7+58 & 7+74 approximately.
3:14pm- 11 joints now placed and fittings wrapped for concrete thrust blocks.
4:22pm- more ditch is opened up and some rock breaking occurring. Storm drains will he dug under next near STA 6+90.