Tuesday, February 9, 2021

Branson Creek Ph 2 - Flat Creek


7:00am- crew will be digging to lay pipe today on 4” line in Pinnacle. 

8:11am- 1st joint is preparing to be laid. 

9:30am- 5 joints have been placed as more rock will be broke now for crossing in roadway. 

11:13am- more rock breaking occurs. 

11:40am- Boyce Excavating fixed MH P8A on map 5 by raising it 18” due to it being lower than the creek. 
12” barrel section and 6” adjustment ring. 



1:25pm- fittings for turn are bolted to pipe now at STA  7+58 & 7+74 approximately. 

3:14pm- 11 joints now placed and fittings wrapped for concrete thrust blocks. 

4:22pm- more ditch is opened up and some rock breaking occurring. Storm drains will he dug under next near STA 6+90.  











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.