Friday, February 12, 2021

Branson Creek Ph 2 - Flat Creek


7:13am- More pipe to be laid. backfill and digging also continues today. 



9:48am- after a slow start due to the cold temps, crew is now setting air release structure at STA 5+07. 

11:06am- a 45* fitting will be placed to align with structure holes. 

12:04pm- pipe now passing through vault with 45* bend attached. 

1:20pm- crew jas now laid 5.5joints of pipe today so far. 

3:07pm- 15.5 joints now placed today. 

3:25pm- 16.5 joints now placed as this will be all that is laid here today due to a sewer line crossing that will need to be done. Excavator will backfill this area and cleanup some. 

4:15pm- backfill now almost complete for the day. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.