7:13am- More pipe to be laid. backfill and digging also continues today.
9:48am- after a slow start due to the cold temps, crew is now setting air release structure at STA 5+07.
11:06am- a 45* fitting will be placed to align with structure holes.
12:04pm- pipe now passing through vault with 45* bend attached.
1:20pm- crew jas now laid 5.5joints of pipe today so far.
3:07pm- 15.5 joints now placed today.
3:25pm- 16.5 joints now placed as this will be all that is laid here today due to a sewer line crossing that will need to be done. Excavator will backfill this area and cleanup some.
4:15pm- backfill now almost complete for the day.