Thursday, February 11, 2021

Branson Creek Ph 2 - Flat Creek


Crew will attempt to work today. 

8:54am- 1st joint of pipe going in now. 

9:51am- 3 joints in as more rock gets broke. 

10:34am- Branson Creek Blvd is getting saw cut today for crossings. 

11:20am- Boyce worked yesterday to complete a repair between FV1I to FV1J, item b) Fieldstone Villas.



1:37pm- while rock is being broke in Pinnacle, another excavator will break rock here at road crossing back to 4”to 6” tie in, STA 16+52 area. 

4:51pm- more 4” pipe is laid for 9 joints total today. Gravel is now going on it to round out the day. 










No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.