7:00am- crew will work to get last part of pipe in from MH B2 to Liftstaion today if rains hold off.
7:48am- crew has decided to tie rebar due to the approaching rains. They didn't want to have a ditch open and it cave in.
8:40am- crew is now back working on B line again.
8:56am- rain begins.
10:14am- rain has stopped and blocks are now placed for pipe and encasement.
11:05am- rebar cages are placed, and crew will begin tying them together.
1:20pm- stacking out MH B2 while awaiting concrete for encasement.
2:42pm- encasement now completed.
4:15pm- meet with Mr Rittenhouse on the access issue at the bridge from 2:50pm to 3:50pm-
Crew is setting ring and casting on B2 now.
5:10pm- MH B2 now finished.