7:02am- crew will be backfilling over concrete encasement from yesterday, move excavator to Fieldstone Liftstaion to backfill there and move valve vault to LS6 site.
7:54am- vaults are getting loaded to be moved.
8:22am- unloading at LS6 site now.
9:14am- gravel going in at Fieldstone Liftstaion where 12” is connected. Cleanup will pursue here.
9:31am- cleanup on line B occurring.
10:10am- backfill at Fieldstone LS.
12:53pm- Fieldstone LS is done again for now as crew will be back on a later date to move forcemain.
2:20pm- roadway intersection will be cut for the tying in of the 6” and 4” forcemains on a later date.
I will now be headed offsite for the rest of the day.