7:07am- crew will be digging today near STA 40+50 today where the 4” and 6” will tie into old 6” forcemain.
9:02am- crew digging to spot utilities as they cross through asphalt intersection.
10:03am- electric and 4” forcemain located.
12:15pm- more digging has occurred. Crew are now under electric lines.
1:27pm- rock breaking now occurring.
3:15pm- rock breaking almost finished then crew will move to LS6 site to get grading done for valve vault.
5:20pm- after some measuring and such rock has been placed and grades checked. This will end the day.