7:08am- crew will work to get valve vault placed today at LS6.
7:45am- gravel going in to continue with leveling grade.
8:50am- grade work is done and blocks are set for placement of vault.
9:38am- lower section of vault now placed.
11:59am- grading work around MH A37 bore pit is wrapping up today.
1:36pm- drain line getting established now in bottom of valve vault.
2:20pm- plastic now placed with just a touch of gravel to hold it in place. Concrete to be poured tomorrow.
3:12pm- crew back at STA 40+50 area to continue uncovering utilities and such. It appears that both Oak Knoll Liftstaion lines may be in the ditch together...?
4:30pm- water line is now located. Crew will place trench plates over trench and clean up a bit to round out their day.