Tuesday, March 23, 2021

Branson Creek Ph 2 - Flat Creek


7:08am- crew will work to get valve vault placed today at LS6. 

7:45am- gravel going in to continue with leveling grade. 

8:50am- grade work is done and blocks are set for placement of vault. 

9:38am- lower section of vault now placed. 

11:59am- grading work around MH A37 bore pit is wrapping up today. 

1:36pm- drain line getting established now in bottom of valve vault. 

2:20pm- plastic now placed with just a touch of gravel to hold it in place. Concrete to be poured tomorrow. 

3:12pm- crew back at STA 40+50 area to continue uncovering utilities and such. It appears that both Oak Knoll Liftstaion lines may be in the ditch together...?

4:30pm- water line is now located. Crew will place trench plates over trench and clean up a bit to round out their day. 












No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.