7:10am- crew will work on D line today at LS6 area.
8:15am- moving rip rap to expose existing gravity line.
8:50am- rip rap is now moved off the line.
10:07am- after a slow dig, crew has located what appears to be concrete encasement of the old sewer line.
11:10am- pipe is getting carried to under the bridge for the Interceptor.
Old homestead is taped off along Interceptor line.
A look at some of the clearing being done.
12:58am- crew will attempt to test 12” line today. Concrete to arrive at 2pm for valve vault at LS6.
1:52pm- test on 12” line from LS to MH A37 is underway.
2:03pm- test finished. Line passes.
2:33pm- concrete begins on valve vault.
4:05pm- concrete is done except for broom finish. It will need to cure out some first.
4:50pm- fittings for LS6 are being loaded and hauled to station site to round out the day.