Wednesday, March 24, 2021

Branson Creek Ph 2 - Flat Creek


7:10am- crew will work on D line today at LS6 area.

8:15am- moving rip rap to expose existing gravity line. 

8:50am- rip rap is now moved off the line. 

10:07am- after a slow dig, crew has located what appears to be concrete encasement of the old sewer line. 

11:10am- pipe is getting carried to under the bridge for the Interceptor. 

Old homestead is taped off along Interceptor line. 

A look at some of the clearing being done. 

12:58am- crew will attempt to test 12” line today. Concrete to arrive at 2pm for valve vault at LS6. 

1:52pm- test on 12” line from LS to MH A37 is underway. 

2:03pm- test finished. Line passes. 

2:33pm- concrete begins on valve vault. 

4:05pm- concrete is done except for broom finish. It will need to cure out some first. 



4:50pm- fittings for LS6 are being loaded and hauled to station site to round out the day. 



















No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.