Crew was able to get ARV plumbed in late yesterday afternoon. Today they will be working to get LS6 wet well cleaned out and begin plumbing it out.
9:04am- Chris’s crew unloads rebar so they can tie encasement for Dennis’s job.
10:00am- one half of the encasement is tied now and will be loaded on trailer.
11:11am- crew still tying rebar for Dennis’s crew.
1:40pm- LS6 wet well is getting cleaned out. I went over everything with Chris about the station and pump setting, guide rails, hatch openings being square, etc.