Wednesday, April 14, 2021

Branson Creek Ph 2 - Flat Creek


Crew has  both lids placed and “level” and “squared” with each other. Went over more things with Chris this morning. 

Grouting around wet well lid will require anti microbial treatment. Chris stated he would get some from Scur Lock. 

9:34am- crew working to get guide rail brackets mounted. 

11:36am- brackets are set in place and a Plumbob will be ised to align pump stands. 






No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.