Monday, April 19, 2021
Branson Creek Ph 2 - Flat Creek
Crew will be moving dirt at LS6 and backfilling behind curbs that were fixed last week.
4:50pm- backfilling behind curbs took place.
Also, LS6 site work took place.
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Branson Creek Ph 2 - Flat Creek
No work onsite this week other than start up at LS6 on Wednesday at 10:00am.
Branson Creek Ph 2 - Flat Creek
Crew to work on encasement area at STA 2+50. 7:25am- digging is started back now to expose area of encasement. 8:50am- 2 joints of 4” now ...
Branson Creek Ph 2 - Flat Creek
6:35am- crane is here and set up for placing of the wet well base today. 7:00am- crew says another foot or so of rock needs to be broke out...
Branson Creek Ph 2 - Flat Creek
11:28am- bore pit at STA 40+00 shows that the ground has been blasted before and Boring Company is not good with drilling through ruble. 11:...