Crew will be working on Fieldstone Liftstaion today to finish converting it to a manhole.
8:12am- crew awaiting Boremans to pump out wet well before by-pass is installed.
9:17am- washing down station now with Boremans pumping.
9:38am- gravel going in now.
9:50am- Jimmy will grade out gravel now.
10:21am- rebar reinforcement is now placed.
12:15pm- flowline is now poured.
5:20pm- forcemain is cur and headed to manhole now. Coring to take place tomorrow. Live flow now going across flowline.