Monday, April 26, 2021

Branson Creek Ph 2 - Flat Creek


Crew will be working on Fieldstone Liftstaion today to finish converting it to a manhole. 
8:12am- crew awaiting Boremans to pump out wet well before by-pass is installed. 

9:17am- washing down station now with Boremans pumping. 

9:38am- gravel going in now. 

9:50am- Jimmy will grade out gravel now. 

10:21am- rebar reinforcement is now placed. 

12:15pm- flowline is now poured. 



5:20pm- forcemain is cur and headed to manhole now. Coring to take place tomorrow. Live flow now going across flowline. 











No comments:

Post a Comment

Branson Creek Ph 2 - Flat Creek

No work onsite this week other than start up at LS6 on Wednesday at 10:00am.